Construction Submittal Process Explained: Steps and Roles

A step-by-step walk through the construction submittal process, from subcontractor preparation to distribution, with who holds the package at each stage, realistic review durations, and what each review stamp commits the reviewer to.

Laptop showing a submittal status list beside a stamped submittal package and an approval stamp at a jobsite, with the title Construction Submittal Process Explained: Steps and Roles

The construction submittal process is the sequence by which a subcontractor proves, before fabrication, that what it intends to install matches what the contract documents require. The subcontractor prepares the package, the general contractor reviews it for completeness and coordination and transmits it, the architect or engineer reviews it for general conformance with the design intent and applies a stamp, and the stamped package goes back down to the field and the fabricator. Each step transfers a defined piece of responsibility.

What is a submittal in construction?

A submittal is any item the contract documents require the contractor to furnish for review before installation: shop drawings, product data, samples, mockups, test reports, certifications, warranties, operations and maintenance manuals, and delegated-design calculations. The specification sections list them, usually in Part 1 of each section, and the submittal register is built from that list during preconstruction.

The purpose is narrow and worth stating precisely. A submittal is not a second design review and it is not a chance to redesign the system. It confirms that the contractor understands the requirement and that the proposed product or fabrication satisfies it. Everything the reviewer writes on it either confirms that understanding or corrects it, and the record of those corrections is what gets read later if the installation fails.

Shop drawings vs product data vs samples

The three principal types carry different levels of contractor authorship, which is why they carry different review exposure.

Type What it is Who prepares it What the reviewer is checking
Shop drawings Project-specific fabrication and erection drawings Subcontractor or fabricator, sometimes sealed by a delegated engineer Conformance with design intent, dimensional coordination, interfaces with adjacent work
Product data Manufacturer catalog literature, marked to identify the specific model and options Subcontractor, from the manufacturer's standard documents That the marked item meets the specified performance, finish and listing requirements
Samples Physical pieces: finishes, colors, textures, fabric, masonry units Subcontractor or supplier Aesthetic and workmanship characteristics that cannot be judged on paper

Shop drawings carry the most risk for the design team, because the contractor is generating new drawings rather than selecting from a catalog. Reviewing them against the contract documents, not against what the fabricator says is standard practice, is the discipline that keeps the review inside its scope.

Submittal process in construction: the steps

1. Build the submittal register (preconstruction, 2 to 4 weeks)

The GC's project engineer reads every specification section and extracts each required item into a register, with the spec section, the responsible subcontractor, the required type and a date driven backwards from the installation date in the schedule. Lead time, fabrication time and review duration all sit between approval and delivery. A register built from the specs but not reconciled against the schedule produces approvals that land after the material was needed.

2. Subcontractor preparation (1 to 4 weeks)

The subcontractor assembles the package, marks the specification section and drawing references, and, for delegated-design items, routes it through its specialty engineer for a seal. This leg is the longest variable in the cycle and the least visible to anyone upstream. A steel fabricator's connection drawings can take a month; a product data sheet for a specified light fixture can take a day.

3. GC review and completeness check (3 to 7 days)

The general contractor reviews and approves the submittal before it goes to the design team. This is a real review, not a forwarding step: dimensions, field measurements, quantities, coordination with other trades, and whether the package is complete enough to be reviewable at all. The GC's stamp affirms that check was made.

This handoff and the one before it are where schedule loss concentrates, because neither is usually logged. A package sitting on a project engineer's desk for nine days because the sub omitted the anchorage calculations does not appear anywhere in the submittal log, which only starts counting when the transmittal is issued.

4. Design team review (10 to 14 calendar days, per most contracts)

The architect of record logs the package, routes consultant-scope items to the structural, mechanical, electrical or civil engineer, consolidates the comments and applies the review stamp. Consultant routing is the hidden leg here. If the architect allows ten days and the MEP engineer takes eight of them, the architect has two days to reconcile and return.

The contractual clock usually runs from receipt of a complete submittal. That phrase matters: returning an incomplete package the day it arrives, rather than reviewing around the gaps, resets the clock and preserves the record.

5. Stamp, distribution and resubmittal (2 to 5 days)

The stamped package returns to the GC, which distributes it to the subcontractor, the fabricator, the field superintendent and the owner's representative, and updates the register with the action and the date. If the action requires a resubmittal, the cycle restarts at step two, and a second full review duration applies.

For a routine item with no exceptions taken, four to eight weeks from preparation to released-for-fabrication is realistic. Anything requiring a specialty engineer's seal, a resubmittal, or a sample approval from the owner runs longer. This is why the submittal log functions as a procurement schedule rather than a compliance document.

Who approves submittals, and what each party is responsible for

Party Action taken What it commits them to
Subcontractor or supplier Prepares and certifies Accuracy of dimensions, quantities, field conditions and means and methods
General contractor Reviews and approves before transmittal Completeness, coordination with other trades, verification of field measurements
Architect of record Reviews, consolidates consultant comments, stamps General conformance with design intent and the information in the contract documents
Consulting engineer Reviews discipline-specific scope Conformance within their discipline, returned to the architect
Owner or owner's rep Approves aesthetic selections, allowance items and substitutions The selection decision, not the technical conformance
Authority having jurisdiction Reviews deferred submittals Code compliance for the deferred system

The word "approved" is doing different work in each row. The design team's action is a review for conformance, not an acceptance of the contractor's construction means, methods, sequences or safety, and it does not relieve the contractor of responsibility for deviations unless the deviation was specifically called out in writing and specifically accepted. That carve-out is why reviewers care so much about stamp language.

What the submittal review stamps actually mean

  • No Exceptions Taken / Approved. The reviewer found nothing contrary to the design intent. Proceed with fabrication. It does not certify dimensions or quantities.
  • Approved as Noted / Make Corrections Noted. Proceed, provided the marked corrections are incorporated. No resubmittal required. If the contractor disagrees with a note, that has to be raised before fabricating, not after.
  • Revise and Resubmit. Deficiencies are substantial enough that the reviewer cannot determine conformance. Do not fabricate. The clock restarts, and the resubmittal should address every comment with a written response.
  • Rejected / Not Approved. The submittal does not comply with the contract documents. Used sparingly, because it tends to invite a commercial argument rather than a technical fix.
  • Reviewed for General Conformance Only. Not a separate action so much as the qualifier printed on most stamps. It states that the review covers general conformance with the design concept and the information given in the contract documents, and expressly excludes dimensions, quantities, fabrication techniques, coordination and safety.
  • For Record / Information Only. No action taken. Used for warranties, certifications and closeout items that require filing rather than review.

Reviewers who hand-write qualifications onto a stamp usually make things worse. A note like "approved subject to field verification of the existing slab elevation" sounds cautious and reads, later, as an instruction the contractor may argue was never clearly assigned. Keep the action in the stamp and put the condition in a numbered comment.

Where submittal schedule loss actually happens

Three failures account for most of it, and none of them are review speed.

The unlogged sub-to-GC leg. The register tracks what has been transmitted. Time spent waiting for a subcontractor to start, or for a fabricator's engineer to seal a calculation, is invisible until someone asks why a four-week lead item has not been ordered.

The completeness check that becomes a review. A GC project engineer who marks up the submittal in detail before transmitting duplicates the architect's work and adds a week. A GC who forwards without reading sends an incomplete package into a 14-day clock, which is worse.

Consultant routing with no internal deadline. If the architect's contract gives 14 days and the consultant is given "a couple of weeks," the architect is late by default. Internal deadlines should be set at roughly 60 percent of the contractual duration.

Fixing these is largely a record problem: knowing who holds each package, how long they have held it, and what was said when it came back. That record is also the firm's defense if the installed work is later disputed. Design teams running RFIs and submittals through construction administration software get the date and action stamps generated automatically rather than reconstructed from email, which is the difference between a position and a recollection. INGENIOUS.BUILD keeps submittals, RFIs, drawings and the correspondence attached to each in one record, and invited collaborators join the projects they work on for free.

For related reading, see how to prevent RFI and submittal delays and where the CA fee goes when tracking architect hours against RFIs and submittals. Firms comparing systems for this work can start with the best software for RFIs, submittals and drawings.

Frequently asked questions

Who approves submittals on a construction project?

The architect or engineer of record takes the review action on submittals, but they do not approve them in a contractual sense. They review for general conformance with the design intent. The general contractor approves the submittal first for completeness, dimensions, field conditions and coordination with adjacent work, and the subcontractor certifies its own content.

What is the difference between shop drawings, product data and samples?

Shop drawings are fabrication and installation drawings prepared specifically for the project by the subcontractor or fabricator. Product data is manufacturer literature for a standard catalog item, marked to show which model and options apply. Samples are physical pieces submitted to establish color, texture, finish or workmanship that cannot be judged from paper.

How long does submittal review take in construction?

Most contracts give the design team 10 to 14 calendar days from receipt of a complete package. The full cycle, from the subcontractor starting preparation to the approved submittal returning to the field, typically runs four to eight weeks for a routine item and longer for anything requiring a specialty engineer or a resubmittal.

What does "approved as noted" mean on a submittal stamp?

Approved as noted means the reviewer accepts the submittal provided the marked corrections are incorporated. The contractor may proceed with fabrication and ordering without resubmitting, as long as the notes are followed. Disagreement with any note must be raised before proceeding, because fabricating against the markups is on the contractor.

What is a deferred submittal?

A deferred submittal is a portion of the design, usually a delegated-design system like fire sprinklers, curtain wall or steel connections, that the building department allows to be submitted after permit issuance. It is prepared and sealed by a specialty engineer, reviewed by the architect or engineer of record, then filed with the authority having jurisdiction before that work begins.

Can a contractor proceed with fabrication before submittal approval?

Only at its own risk, and most contracts say so explicitly. Fabricating or ordering ahead of an approved or approved-as-noted stamp means the contractor absorbs the cost of rework if the reviewer takes exception. Where the schedule demands it, document the decision and the risk acceptance in writing rather than relying on a verbal go-ahead.

RFIs to punch lists

RFIs and submittals, out of the inbox.

RFIs, submittals, drawings, inspections, daily reports and punch lists in one platform.

Step 1 of 2

Book a demo

Two quick steps, then pick a time.

Used only to schedule and prep your demo. Privacy